HQ 2.0 Syncronization Error

In HQ syncronization processing worksheet 401, after aprox 2hours akes , The message appear: Timeout Operation is not allowed when the oject is closed. (Unhandled error, state='9') In verified that the HQ Server and HQ Client is the same version. SO and HQ are running under SQL2005 (express and server).

Reply to
Jbcc
Loading thread data ...

Did you test database connectivity and network connections on both HQ Client and HQ Server? Are they successful on both ends?

If so, try deleting the 401 that is not processing successfully in HQ Manager, create a new 401 and see if that one processes okay.

H> In HQ syncronization processing worksheet 401, after aprox 2hours akes , The

Reply to
convoluted

Are the other stores processing 401 successfully?

Reply to
Ahmed Nashat

Yes Convoluted. Im Test de Connectivity on Both Client and Server, in the sync process all worksheet work Ok but when 401 is running the when the status show about 60mb bytes transfered the error is done. Im deleted de 401 and create it again, but the error its again.

I need to Sync because is new >

Reply to
Jbcc

Reply to
Jbcc

Hi

Its probably the latest hotfix which has destroyed your communicati> I have 8 Store working with V1.2 and SQL2000 (HQ and SO), so i decided to

Reply to
Shaun

BeanSmart website is not affiliated with any of the manufacturers or service providers discussed here. All logos and trade names are the property of their respective owners.