Today i had a till error (or more a windows error!) whereby the registery on till 3 had corrupted, i was unable to fix this quickly, and on St. Patricks day it was hell being 1 till short.
My question is as follows!
I want to set up a complete unit for a spare - i understand my licene will only let me use my defined amount of tills at the same time, but i was thinking i could i set up a new till as a spare which can be linked to a training database for staff training ect then moved into the shop when one of our tills fails. ( i wouldnt need extra licences, just new hardware)
Can somebody tell me which configurations i will need to change when i swap one for the other? Or is that not nececary? Should i just set up this new till as a completely new till with new till number which will only run (because of licence constraint) when another till is closed? I can move it from the training database to the live database when it needs moved out onto the shop floor....
Any advice on this would be greatly appreciated!